Announcements‎ > ‎

Gas Works Construction

posted May 10, 2013, 7:28 AM by lsna webmaster   [ updated May 10, 2013, 7:30 AM ]

There were three crews in action last week. The contractor's crew installed 130' of pipe on 22nd between Cherry and Race. A PGW crew has been on site to 'cut and cap' the 20" gas main on 22nd St between Arch & Cherry and on Cherry between 22nd & Van Pelt. The contractor's crew will continue on 22nd between Cherry and Race through today. Last Friday they were to return to 22nd  between Arch and Cherry to complete work on the the east curb line crossing 22nd St to the west side and to begin installing the new main just north of Cherry. 

 

Click here for a street map with a schedule.

Comments